Dubai Airports schedules southern runway upgrade at Dubai International

Dubai Airports plans to close Dubai International airport’s southern runway for 45 days from 16 April to 30 May in 2019 to conduct an upgrade.
It says the dates correspond to a historical trough period, but even so, airlines will be required to reduce their operations to and from the airport during the program.

 